top of page

Too Big to Build

Writer: Alexander Kardos-Nyheim
Alexander Kardos-Nyheim
Nov 11
9 min read

How London's largest consented schemes became monopolies over the future of whole neighbourhoods, and a formula for unblocking them



UDRO is grateful for the continued assistance of Conrad O'Callaghan, Harry Fang and Alara Tosun in spearheading the policy proposals to improve how London develops.


Terence Williams lives a short walk from Millwall's ground in South Bermondsey, on land that has sat inside the red line of a single developer's masterplan for well over a decade. He did not choose to be part of the New Bermondsey scheme. He has no say in when it happens, what it looks like, or whether it happens at all. There is one realistic buyer for his property, and that buyer sets the pace. The planned Surrey Canal Overground station will sit within about fifty yards of his front door. For now, the uplift it brings will go to whoever controls the scheme, not to him.


Mr Williams is not unusual. Lewisham alone holds three consents of this kind: Renewal's New Bermondsey, Hutchison's Convoys Wharf in Deptford and Landsec's redevelopment of Lewisham Shopping Centre. Between them they cover roughly 8,700 homes. Each was presented as a major contribution to London's housing supply. Each has turned out slower, smaller or more conditional than promised.


Our argument is simple. These schemes have become victims of their own size. The scale that made them attractive to planners has handed single companies a monopoly over the future of whole districts. When they stall, they deliver nothing at all. The way out is to break them up: sell or compulsorily acquire parts of these sites, and let councils, community land trusts, small builders and existing owners build on them at a human scale. That is the other half of planning reform, and it is missing from the national debate.


The arithmetic of nothing


A large masterplan is an all-or-nothing bet. If everything goes to plan, it delivers thousands of homes. If anything goes wrong, it delivers close to none.


New Bermondsey shows the problem most clearly. Renewal first won permission for the Surrey Canal site in 2012, for 2,500 homes. It was approved again in 2022 at around 3,500 homes, and re-approved in 2024 [2][18]. Phase 1 has detailed consent for 600 homes. The remaining 2,900 are tied to the new station by a Grampian condition: development pauses at 600 homes until construction of the station begins [3]. The station's detailed design is not expected to finish until early 2028, and main works depend on government funding that has not yet been secured [3]. Meanwhile, Renewal's £25 million contribution to the station has already cost the scheme 100 affordable homes in phase 2, where provision fell from 35 per cent to 17.6 per cent [1][2]. In other words, 2,900 homes are waiting on a station that does not yet have its money.


Convoys Wharf is the same story on the river. Hutchison bought the former royal dockyard from News International in 2008. In 2014, then-Mayor Boris Johnson called the application in and approved it, overruling Lewisham Council [4]. The developer had argued that a decision was urgent [22]. Construction on the first plot did not begin until late 2021 [5]. The current reserved matters cover 456 private and 124 affordable homes, out of a promised 3,500 across 22 plots [6].


Lewisham Shopping Centre was approved in October 2025 for 1,744 homes. Only 98 are for social rent [7]. Most of the affordable housing sits in later, outline-only phases [7], in a build programme expected to run for around a decade [23]. The full scheme also relies on the council compulsorily acquiring Lewisham House, a neighbouring building whose owner objected [8].


None of this is unique to Lewisham. In 2018, Sir Oliver Letwin's review for the Treasury found that the median build-out period on the large sites he examined was 15.5 years, about 6.5 per cent of a site a year. Build-out in London was slower still [9]. His diagnosis was not land-banking. It was that a single developer building one kind of home can only sell as fast as the local market will absorb it. Such a scheme moves at the speed of its own sales office.


Monopoly by masterplan


Scale also changes who holds the power.


Once a site of this size is consented to one company, everyone inside it becomes a captive seller. Owners like Mr Williams cannot sell to anyone else at a fair price, because no one else can do anything with the land. They cannot build themselves, because their plot has been drawn into someone else's masterplan. Their only option is to wait. The developer, meanwhile, can wait longer and has every reason to. It can let rented stock run down, let neighbouring land fall into disuse, and allow conditions to deteriorate until holdouts settle. According to evidence UDRO has seen, residents at New Bermondsey have lived with exactly this for fifteen years: higher rents on properties the developer has acquired, car repairs spilling onto the street beside a children's playground, and rubbish left to overflow. Renewal itself has said that an independent inquiry into the scheme caused it to miss a 2018 funding deadline [18]. In any other market this would be called market power. Planning has no word for it, and no remedy.


The same concentration flattens the city. A single developer working to a single design code produces a single kind of place: towers of similar height, similar materials, similar tenures and similar ground floors. Local campaigners have called the Convoys Wharf design an "anywhere design" [4]. That may be unfair to the architects, but it is a fair description of what happens when 16.6 hectares of Henry VIII's royal dockyard is handed to one client [6]. Districts that grew plot by plot over centuries are rebuilt in one go.


Lewisham's planners know the outcome they want. The borough's Local Plan sets a 50 per cent affordable housing target [19]. Large schemes negotiate that target down on viability, then phase the affordable homes to the end, then stall. The planning system treats the scheme as indivisible, so the council's only leverage is to refuse it whole or accept it whole.


London has done this before


The alternative has been tried. London has done it before, and Lewisham more than most.

Coin Street, 1984. Thirteen acres of the South Bank, between Waterloo and Blackfriars, were earmarked for offices and what would have been Europe's tallest hotel [20]. After two public inquiries and a change of administration, the Greater London Council changed course [10]. It used planning policy to limit the land's value from about £4 million to £1 million [11]. It bought out the commercial developer, Greycoat, and days later sold the whole site to a local non-profit, Coin Street Community Builders, for £1 million, on condition it was used for social housing [10]. Forty years on, the site holds housing co-operatives, a riverside park and Oxo Tower Wharf, and it is still run by and for the neighbourhood [20].


Church Grove, Ladywell. In 2016, Lewisham Council granted a disused school site to the Rural Urban Synthesis Society, a local community land trust, on a 250-year lease. The Mayor of London added £988,000 [12]. Residents co-designed the homes and many built or finished their own. In 2024, families moved into 36 permanently affordable flats, the largest community-led self-build in the capital [13]. Lewisham was also where Walter Segal's self-build homes went up in the 1970s and 1980s.


Small Sites, Small Builders. Since 2018, City Hall has brought small public sites to market for small builders and community groups, through a single portal and standard contracts. Eighteen public landowners have released 72 sites through it [14].


In each case, the size of the plot was a decision someone made. When land is divided into pieces that local organisations can take on, homes get built at a pace and character that a single masterplan does not deliver. Letwin reached a similar view. He recommended that sites of over 1,500 homes be required to offer a much wider range of homes and tenures, and that in future large sites be split into parcels for different builders [9].


A formula for unblocking


We propose a five-part formula. Councils can apply it to Lewisham's three schemes now, and government can extend it to every stalled large site in the country.


1. A delivery clock. Every consent above 1,000 homes should carry a published delivery trajectory. If a scheme falls materially behind it, for example by delivering less than a quarter of its homes within seven years of outline consent, the council can require part of the site to be released. The developer keeps what it is actually building. It loses the right to sit on the rest.


2. Sell first, compel second. The first step is a negotiated sale of parcels to the council or to community bodies at a fair price. If that fails, compulsory purchase is the backstop. Since 2024, councils have been able to ask for CPOs that deliver affordable or social housing to be paid at existing use value, without "hope value" for permissions that may never be built [15]. A stalled consent is the clearest case for using that power.


3. Parcel the land. Released land should be divided into plots that small and local organisations can realistically take on: a few dozen homes, not a few thousand. Some should go to the council's own building programme, some to community land trusts and co-operatives, and some to small builders through the existing Small Sites portal.


4. Bring existing owners in, not out. People like Mr Williams should not be treated as obstacles to be bought out at the lowest possible price. They should be able to develop their own land, alone or with neighbours, within the rules of the wider plan. Germany and Japan have long used land readjustment, in which owners pool their plots, the area is replanned with roads and services, and each owner receives a smaller but more valuable plot back. A London version would turn holdouts into builders.


5. Keep the masterplan, drop the monopoly. Much of the expensive work in these schemes is already done: the station, the roads, the river walk, the infrastructure obligations. That framework should survive as a design code and an infrastructure plan, binding on everyone who builds on the site. What should go is the assumption that one company must build all of it.


The other half of planning reform


For most of the past decade, planning reform has mainly meant removing obstacles in the way of large developers. Some of that was needed. But it treats delivery as a question of permission, when the Lewisham schemes have had permission for years. The bottleneck is no longer the planning committee. It is the structure of ownership the committee has created.

The Prime Minister has said he wants to take power out of Westminster and carry it into every postcode [16]. The English Devolution and Community Empowerment Act 2026 has given communities new rights, and the government has announced a £61 million Pride in Place Community Right to Buy Fund to help them take over local assets [17]. These are the right instincts, but they are aimed at pubs and community centres. The largest assets in most neighbourhoods are the stalled development sites around them, and nothing in current policy gives communities a way in.


We ask the government to close that gap in three ways:


  • Extend the Community Right to Buy to stalled consented land, so that community land trusts and residents' groups get a right of first refusal when parcels are released under a delivery clock.

  • Create a national community land fund for acquiring and preparing parcels on stalled large sites, recycled as homes are sold or let. Coin Street shows what land bought at a fair price, rather than a speculative one, can sustain for forty years [10][11].

  • Write the delivery clock into national policy, along with a presumption in favour of hope-value-free CPOs where a large consent has stalled.


In Lewisham, the new administration has an opening to go first. The Mayor has pledged to stand up to developers and deliver more genuinely affordable homes [21]. The three schemes in this paper are the obvious test. UDRO has raised them directly with the Mayor, and we stand ready to work with the council on putting this formula into practice. Mr Williams and his neighbours have waited fifteen years for one company to decide their future. They should be allowed to help build it themselves.


References

  1. Inside Housing, "Developer halves affordable housing in second phase of Lewisham scheme after £25m train station cost".

  2. Estates Gazette, "Renewal's £1.9bn New Bermondsey masterplan receives approval".

  3. ianVisits, "Additional funding found to push ahead with new London Overground station", 17 September 2025.

  4. The Developer, "Deptford docks: There will be no references left of what's there".

  5. From the Murky Depths, "Construction finally begins at Convoys Wharf development in Deptford", 10 November 2021.

  6. Hutchison Property Group, "The Masterplan Delivers", Convoys Wharf.

  7. Greenwich Wire, "Plans for 1,700 flats at Lewisham Shopping Centre set for approval", 9 October 2025.

  8. Greenwich Wire, "Lewisham Shopping Centre redevelopment approved", 18 October 2025.

  9. Sir Oliver Letwin, Independent Review of Build Out: Final Report, Cm 9720, HM Treasury and MHCLG, October 2018.

  10. Labour Hub, "A tribute to George Nicholson", 11 June 2026.

  11. Community Led Housing London, "Coin Street".

  12. Mayor of London, "Mayor backs community plans for self-build homes", 5 October 2018.

  13. Ladywell Live, "Families move into 36 RUSS community-led self-build homes in Ladywell", 10 June 2024.

  14. Mayor of London, "Small Sites for Small Builders site release fund".

  15. MHCLG, "Compulsory purchase compensation: power to remove hope value".

  16. Public Sector Executive, "Mayors to share income tax revenues in biggest devolution shift in a generation".

  17. Ward Hadaway, "Community empowerment initiatives announced by the UK Government", 2026.

  18. East London Lines, "New Bermondsey housing scheme".

  19. London Borough of Lewisham, "Councils launch legal challenge to stop Mayor of London cutting affordable housing", 2026.

  20. Coin Street Community Builders, "A walk through our neighbourhood".

  21. South London News, "Who runs Lewisham", 2026.

  22. From the Murky Depths, "Convoys Wharf: Consultation on next phase in Deptford", 24 July 2021.

  23. Construction Enquirer, "£1.3bn revamp plan for South London shopping centre", 5 November 2024.

 
 
 

Comments


bottom of page